Project Timeline
Milestones
- December 2014 Project Approval in Principle by Board of Governors
- January & February 2015 User Consultations and Design Team Selection
- March to December 2015 Design and Construction Documents Preparation
- January to April 2016 Tender for Construction Issued
- May 2016 to August 2017 Construction
- September 2017 Opened